2019年12月30日上午10点15分,经过76个小时的紧张施工,山东济南一栋重达8000吨的5层办公楼实现平移,向东移动米,这是山东省内首例因高速公路建设导致的楼房平移工程,创造了同类移楼的山东最快速度。

At 10.15 a.m. on December 30,2019, after 76 hours of intense construction, a five-story office building weighing 8000 tons in Jinan, Shandong Province, shifted to the east, the first in Shandong Province to create the fastest speed of the same kind of moving building.

  据了解,这栋大楼是济南一家混凝土公司的办公楼,因为济南大东环高速设计路线经过该楼,为满足原单位生产需求、节约建设成本,最终方案为该办公楼往东平移,从2019年10月18日开工,历时74天,实际移楼时间3天,持续有效平移工作时间32小时。山东建大工程鉴定加固研究院设计部主任夏风敏表示,这个项目没有选择把大楼拆除重建,而是采用平移的方式,可节省接近三分之二的成本。(央视记者窦效磊)

It is understood that the building is the office building of a concrete company in Jinan, because the high-speed design route of Jinan Dadonghuan passes through the building, in order to meet the production needs of the original unit and save the cost of construction, the final plan is for the office building to move eastward, starting on October 18,2019, which lasts 74 days, the actual moving time is 3 days, and the working time is 32 hours continuously and effectively translated. Xia fengmin, director of the design department of the shandong jianda institute for engineering appraisal and reinforcement, said the project did not choose to demolish and rebuild the building, but would save nearly two-thirds of the cost by means of translation. (CCTV reporter Dou Xiaolei)


欢迎转载,转载请注明出处:英皇app下载